Construction Cost
Synonyms: Building Cost، Hard and Soft Costs، Build Cost
Last updated: 2026-09-25
Short Definition
Construction cost is the total amount spent to build a structure until it is ready for occupancy, including direct costs (materials, labour, equipment and the contractor's profit) and soft costs (design, supervision, permits, soil testing, insurance and financing), usually excluding land value.
Overview
Legal Basis
The Civil Transactions Law (Royal Decree No. M/191 dated 29/11/1444H) governs the effect of pricing in construction contracts: Art. 470 (unit-rate estimates, the duty to notify immediately of an apparent overrun, and the owner's right to withdraw if the overrun is grave), Art. 471 (a lump-sum price does not increase with material or labour prices; the court may restore the contractual balance in general exceptional circumstances) and Art. 472 (fair remuneration if no price was set). The Saudi Building Code Implementation Law (M/43) makes code compliance a permit condition, and the Organization of the Saudi Contractors Authority (Cabinet Decision No. 510 dated 23/11/1436H) empowers the Authority to set indicators for building-material prices and contractor rates (Art. 3).
Practical Example
An owner estimates the cost of a 500 m² villa in Dammam: shell 500 × 850 = SAR 425,000 and finishing 500 × 1,000 = SAR 500,000, giving a direct cost of SAR 925,000, plus 15% VAT on the contract (SAR 138,750) because the contractor is VAT-registered. Soft costs: design 20,000, supervision 25,000, soil test 4,500 and permit fees and inherent defects insurance of about 15,000, i.e. SAR 64,500. A contingency of 5% of direct cost adds SAR 46,250. The total is about SAR 1,174,500, roughly SAR 2,349 per m² including VAT. Because the contract is lump-sum, the contractor cannot later demand more merely because steel prices rose.
Common Mistakes
- ✗Comparing contractor bids by price per square metre only, without matching specifications, bills of quantities and what the price includes or excludes.
- ✗Ignoring soft costs (design, supervision, soil test, inherent defects insurance and fees) and a contingency reserve.
- ✗Not stating whether the price includes the 15% VAT or is exclusive of it.
- ✗Accepting price-increase claims under a lump-sum contract because of rising prices, although the law only allows this in general exceptional circumstances assessed by the court.
- ✗Confusing construction cost with the property's market value when financing or selling.
International Differences
Many countries use official construction-cost indices to adjust long contracts, and some international standard forms (such as FIDIC contracts) allow price-adjustment clauses. In Turkey, the Ministry of Environment, Urbanisation and Climate Change publishes annual approximate unit construction costs per square metre by building class. In Saudi Arabia, the default under a lump-sum contract is no increase, with judicial rebalancing possible in general exceptional circumstances, so any price-adjustment mechanism should be written expressly into the contract.